Place Toulouse, France | Duration 2005-2011 |
Project Manager Aéroport Toulouse Blagnac | Amount 80M and 10M euros |
Project
- Construction of Terminal D from 2005 to 2010: expansion of the airport with the construction of Hall 3
- Construction of Parking Silo 2 on the terminal site from 2009 to 2011
Solution: eProject EDM
Supply and implementation of a document exchange and collaborative project management system. Assistance in the implementation, training and general management of the project. Implementation of the EDI server of the graphic documents and the technical documents of the building site. Training, assistance to the users, follow-up of the implementation of the system and accompaniment throughout the project.